UPDATE:  PAVING ON THESE STREETS HAS BEEN POSTPONED TO MONDAY, OCTOBER 18 DUE TO RAIN IN THE FORECAST

Day #1:  Mill and make base repairs to Fair Acres & Esther Drives

Day #2:  Mill and make base repairs to Winding Way

Day #3:  Mill and pave Section Road

Day #4:  Base repairs to Galbraith Road and pave side streets

Please note that work may spill over into the following week depending on weather and progress.  Typically, the week following paving once all streets are complete and have been permitted to set, a rejuvenate is applied to the newly-surfaced street which can double the life of the new pavement.  Please contact the Amberley Village Administrative Offices with any questions or for specific or additional information.

RESIDENTS AND TRAVELERS ARE URGED TO FIND ALTERNATE ROUTES DURING THE WEEK AND INTO THE WEEK OF THE 18TH TO ALLOW FOR POSSIBLE SCHEDULING ADJUSTMENTS